New Build Update January

24th January 2020
Message from site Manager:

Works are progressing well, we have almost completed the doors and over the next week we will be installing the architraves and skirting. Painters are due back on site in another week to get everything up to undercoat level. The floors will be going down in two to three weeks and in 6 weeks we will have the furniture fitted. The mechanical and electrical installation will be complete in another month.

Hybrid hall/ kitchen area

The timber walls are constructed and over the next two weeks we will have them insulated and plasterboarded. The brickwork to the external walls will commence on Monday and the render works will follow in about two weeks. All should be complete in about a month (weather dependant).

Externally the ground workers will start on the footpaths in the next week or two. The scaffold will continue to be dismantled where possible. 90% of all drainage works are complete.

Overall progress is further advanced than expected.