Update from the site manager for our new build:

As you can see from the photos, works are progressing well despite some of the awful weather we have had. The foundations for the modular units are ready and we have started on the hall slab.

There are a few obstacles left before we install the modular units but if these go well then during half term we intend to deliver and install the modular units so when you return to school part of the new building will be on site.

Over the rest of November we will be preparing and completing the rest of the hall slab and hopefully starting the brick outer skin of the building.

 

 Michael Swain

 Site Manager

 